Butterfly Gardens Pavement Reconstruction and Planted Area Expansion

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Butterfly Gardens including new pavements, fencing, benches, and trash receptacles and expanded planted areas.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: March 2017
Completion Date: August 2017

Construction

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $641,000
Funding Sources:
  • Mayoral
  • Borough President

Location

Butterfly Gardens , Brooklyn
7th Avenue and 18th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/16/2018