West Bronx Recreation Center AC Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the air conditioning system for the gymnasium at West Bronx Recreation Center.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: June 2016
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017
Completion Date: July 2018

Construction

Start Date: October 2018
Projected Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $909,000
Funding Source: Mayoral

Location

West Bronx Recreation Center , Bronx
1527 Jesup Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/16/2018