West Bronx Recreation Center AC Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the air conditioning system for the gymnasium at West Bronx Recreation Center.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: June 2016
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017
Completion Date: July 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

West Bronx Recreation Center , Bronx
1527 Jesup Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 08/17/2018