West Bronx Recreation Center AC Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    98% complete

This project will reconstruct the air conditioning system for the gymnasium at West Bronx Recreation Center.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: June 2016
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017
Completion Date: July 2018

Construction

Start Date: October 2018
Projected Completion Date: October 2019
Adjusted Completion Date: January 2020

Understand how we build parks.

Funding

Total Funding: $1,048,000
Funding Source: Mayoral

Location

West Bronx Recreation Center , Bronx
1527 Jesup Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/11/2019