Patterson Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    79% complete

This project will reconstruct the playground and basketball courts at Patterson Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: October 2017
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018
Completion Date: February 2019

Construction

Start Date: June 2019
Projected Completion Date: June 2020

Understand how we build parks.

Funding

Total Funding: $4,530,000
Funding Sources:
  • Mayoral
  • City Council

Location

Patterson Playground , Bronx
East 145th Street, Morris and Bronx Avenues.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 04/01/2020