Patterson Playground Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the playground and basketball courts at Patterson Playground.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: October 2017
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • City Council

Location

Patterson Playground , Bronx
East 145th Street, Morris and Bronx Avenues.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/07/2018