Corlears Hook Park Dog Run Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the dog run at Corlears Hook Park, adding stable ground surface, water features and dog waste containers, and replacing fencing.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Corlears Hook Park , Manhattan
Cherry Street, Jackson Street, FDR Drive

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/16/2018