Corlears Hook Park Dog Run Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the dog run at Corlears Hook Park, adding stable ground surface, water features and dog waste containers, and replacing fencing.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • City Council

Location

Corlears Hook Park , Manhattan
Cherry Street, Jackson Street, FDR Drive

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 06/25/2019