John Jay Park Adult Fitness Area Reconstruction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the adult fitness area in John Jay Park.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Start Date: March 2018
Projected Completion Date: March 2019

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

John Jay Park , Manhattan
FDR Drive between East 76th Street and East 78th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/16/2018