John Jay Park Sitting Area Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the sitting area at John Jay Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: June 2019

Procurement

Start Date: June 2019
Projected Completion Date: March 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

John Jay Park , Manhattan
FDR Drive between East 76th Street and East 78th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 09/20/2019