Thomas Jefferson Park Irrigation Installation

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will install new irrigation and paths at Thomas Jefferson Park.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: February 2016
Projected Completion Date: February 2017
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • City Council

Location

Thomas Jefferson Park , Manhattan
First Avenue between East 111th Street and East 114th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/17/2018