Jacob H. Schiff Playground Basketball and Handball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct basketball and handball courts at Jacob H. Schiff Playground.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: May 2018

Procurement

Start Date: May 2018
Projected Completion Date: February 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • City Council

Location

Jacob H. Schiff Playground , Manhattan
Amsterdam Avenue Between 136th Street and 138th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/19/2019