Jacob H. Schiff Playground Basketball and Handball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct basketball and handball courts at Jacob H. Schiff Playground.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: May 2018

Procurement

Start Date: May 2018
Projected Completion Date: February 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: City Council

Location

Jacob H. Schiff Playground , Manhattan
Amsterdam Avenue Between 136th Street and 138th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/10/2018