Jacob H. Schiff Playground Basketball and Handball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct basketball and handball courts at Jacob H. Schiff Playground.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: June 2017
Projected Completion Date: June 2018
Completion Date: May 2018

Procurement

Start Date: May 2018
Projected Completion Date: February 2019
Completion Date: June 2019

Construction

Start Date: August 2019
Projected Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $1,023,000
Funding Sources:
  • Mayoral
  • City Council

Location

Jacob H. Schiff Playground , Manhattan
Amsterdam Avenue Between 136th Street and 138th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 10/22/2019