Loreto Playground Asphalt Multi-Purpose Play Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    8% complete

This project will construct an expanded asphalt multi-purpose play area in Loreto Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2018
Projected Completion Date: February 2019
Completion Date: February 2019

Procurement

Start Date: February 2019
Projected Completion Date: November 2019
Completion Date: November 2019

Construction

Start Date: September 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $2,000,000
Funding Sources:
  • Mayoral
  • Borough President
  • State

Location

Loreto Playground , Bronx
Morris Park Avenue, Tomlinson Avenue, Haight Avenue, and Van Nest Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/19/2020