Loreto Playground Asphalt Multi-Purpose Play Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    60% complete

This project will construct an expanded asphalt multi-purpose play area in Loreto Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: February 2018
Projected Completion Date: February 2019
Completion Date: February 2019

Procurement

Start Date: February 2019
Projected Completion Date: November 2019
Completion Date: November 2019

Construction

Start Date: September 2020
Projected Completion Date: September 2021
Adjusted Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $2,000,000
Funding Sources:
  • Mayoral
  • Borough President
  • State

Location

Loreto Playground , Bronx
Morris Park Avenue, Tomlinson Avenue, Haight Avenue, and Van Nest Avenue

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 05/20/2022

Was this information helpful?