Playground Thirty Five XXXV Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    3% complete

This project will reconstruct Playground Thirty Five XXXV.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: April 2018

Construction

Start Date: May 2018
Projected Completion Date: May 2019

Understand how we build parks.

Funding

Total Funding: $2,175,000
Funding Source: Mayoral

Location

Playground Thirty Five XXXV , Queens
35th Avenue between Steinway Street and 41st Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/17/2018