Prospect Park Flatbush Avenue Perimeter Sidewalk Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    23% complete

This project will reconstruct the damaged sidewalk and fencing along Flatbush Avenue. The new sidewalk will have exposed aggregate concrete, new ornamental fencing, a double row of street trees, benches, and light poles.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: June 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: October 2017

Construction

Start Date: November 2017
Projected Completion Date: November 2018
Adjusted Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $1,745,000
Funding Sources:
  • Borough President
  • City Council

Location

Prospect Park , Brooklyn
West side of Flatbush Avenue, from Grand Army Plaza to Prospect Park Zoo

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/16/2018