Van Nest Flag Pole and Plaza Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct a flagpole and reconstruct a portion of the plaza in Van Nest Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: February 2016
Projected Completion Date: November 2016
Completion Date: March 2017

Procurement

Start Date: March 2017
Projected Completion Date: December 2017
Completion Date: November 2017

Construction

Start Date: February 2018
Projected Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $417,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Van Nest Park, Bronx
Van Nest Park, Mead Street, White Plains Road, Unionport Road

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 02/16/2018