Wakefield Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    93% complete

This project will reconstruct Wakefield Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2016
Projected Completion Date: January 2018
Completion Date: January 2019

Procurement

Start Date: January 2019
Projected Completion Date: October 2019
Completion Date: May 2021

Construction

Start Date: June 2021
Projected Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $5,276,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Wakefield Playground , Bronx
Carpenter Avenue between East 239th Street and East 240th Street

 

Project Staff

Project Liaison: Mike Ortiz
Contact NYC Parks about this project

Last updated: 05/25/2022