Hell Gate Pathway Construction Phase 3

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct a multi use pedestrian pathway under the Amtrak Viaduct at Wards Island Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: January 2016
Projected Completion Date: January 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: May 2018

Construction

Start Date: December 2018
Projected Completion Date: May 2020

Understand how we build parks.

Funding

Total Funding: $3,404,000
Funding Sources:
  • Mayoral
  • Borough President
  • State
  • Federal

Location

Wards Island Park , Manhattan
Under the Amtrak Viaduct from Hell Gate Bridge to Column 27 and Central Road

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/16/2018