Hell Gate Pathway Construction Phase 3

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct a multi use pedestrian pathway.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: January 2016
Projected Completion Date: January 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • State
  • Federal

Location

Wards Island Park, Manhattan
BELOW THE AMTRAK VIADUCT, FROM THE HELL GATE BRIDGE ABUTMENT TO COLUMN 27 AND CENTRAL ROAD

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 02/16/2018