Flushing Meadows Corona Park Mauro Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Mauro Playground in Flushing Meadows Corona Park.

Project Timeline

Design

Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: April 2019

Construction

Start Date: April 2019
Projected Completion Date: October 2020
Completion Date: November 2019

Understand how we build parks.

Funding

Total Funding: $5,000,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Flushing Meadows Corona Park , Queens
Park Drive East at 73rd Terrace

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 07/05/2022

Was this information helpful?