Forest Park Glendale Entrance Construction
-
100% complete
-
100% complete
-
62% complete
This project will construct a new multi-use bicycle and pedestrian pathway into Forest Park from Myrtle Avenue, including streetscape and park pathway improvements.
Project Update: This project is in active construction.
Project Timeline
Design
Start Date: April 2017
Projected Completion Date:
April 2018
Completion Date:
July 2019
Procurement
Start Date: July 2019
Projected Completion Date:
April 2020
Completion
Date:
August 2021
Construction
Start Date: September 2021
Projected Completion Date:
September 2022
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
- City Council
Location
Forest Park
, Queens
Forest Park Drive and Myrtle Avenue
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 05/20/2022