Forest Park Glendale Entrance Construction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct a new multi-use bicycle and pedestrian pathway into Forest Park from Myrtle Avenue, including streetscape and park pathway improvements.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: April 2017
Projected Completion Date: April 2018
Adjusted Completion Date: May 2018

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • City Council

Location

Forest Park , Queens
Forest Park Drive and Myrtle Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 02/22/2019