Nautilus Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct Nautilus Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: January 2019
Projected Completion Date: January 2020
Completion Date: May 2020

Procurement

Start Date: May 2020
Projected Completion Date: February 2021
Completion Date: April 2022

Construction

Start Date: August 2022
Projected Completion Date: August 2023

Understand how we build parks.

Funding

Total Funding: $5,808,000
Funding Sources:
  • Borough President
  • City Council

Location

Roy Wilkins Recreation Center , Queens
Merrick Boulevard and Baisley Boulevard

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 07/01/2022