Forest Park Pathways Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct pathways and the plaza around the visitor center at Forest Park.
Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.
Project Timeline
Design
Start Date: January 2020
Projected Completion Date:
June 2020
Completion Date:
June 2020
Procurement
Start Date: June 2020
Projected Completion Date:
March 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Forest Park
, Queens
Woodhaven Boulevard between Myrtle Avenue and Forest Park Drive
Project Staff
Project Liaison: Joanne Amagrande
Contact NYC Parks
about this project
Last updated: 01/19/2021