World's Fair Playground Asphalt Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the asphalt field at World's Fair Playground in Flushing Meadows Corona Park.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: May 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: April 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Borough President

Location

Flushing Meadows Corona Park , Queens
along the Grand Central parkway near 62nd road in the Borough of Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 04/20/2018