Cunningham Park Lower Playground Tot Lot Reconstruction
-
100% complete
-
100% complete
-
29% complete
This project will reconstruct the Lower Playground (Redwood Playground) in Cunningham Park.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: June 2016
Projected Completion Date:
June 2017
Completion Date:
July 2017
Procurement
Start Date: July 2017
Projected Completion Date:
April 2018
Completion
Date:
June 2018
Construction
Start Date: July 2018
Projected Completion Date:
July 2019
Adjusted Completion
Date:
December 2019
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
- City Council
Location
Cunningham Park
, Queens
193rd Street and Aberdeen Road