Cunningham Park Lower Playground Tot Lot Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    10% complete

This project will reconstruct the Lower Playground (Redwood Playground) in Cunningham Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: June 2017
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018
Completion Date: June 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $1,693,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Cunningham Park , Queens
193rd Street and Aberdeen Road

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 12/14/2018