Rainey Park Playground, Picnic Grove and Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the playground, picnic grove and basketball court at Rainey Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: September 2021

Procurement

Start Date: September 2021
Projected Completion Date: June 2022
Adjusted Completion Date: January 2023

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Borough President
  • City Council

Location

Rainey Park , Queens
Vernon Boulevard between 34th Avenue and 33rd Road

 

Project Staff

Project Liaison: Mike Dockett
Contact NYC Parks about this project

Last updated: 08/12/2022