Rainey Park Playground, Picnic Grove and Basketball Court Reconstruction
-
100% complete
-
5% complete
-
0% complete
This project will reconstruct the playground, picnic grove and basketball court at Rainey Park.
Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.
Project Timeline
Design
Start Date: May 2019
Projected Completion Date:
May 2020
Completion Date:
September 2021
Procurement
Start Date: September 2021
Projected Completion Date:
June 2022
Adjusted Completion
Date:
January 2023
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Rainey Park
, Queens
Vernon Boulevard between 34th Avenue and 33rd Road
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 08/12/2022