Newtown Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct paths and plantings on the upper lawn area of Newtown Playground.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: June 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: July 2018

Construction

Start Date: September 2018
Projected Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $1,315,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Newtown Playground , Queens
92nd Street and 56th Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/20/2018