Glen Oaks Oval Playground Reconstruction and Adult Fitness Equipment Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    58% complete

This project will reconstruct the playground and replace the basketball court with an adult fitness equipment area at Glen Oaks Oval.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: August 2019

Construction

Start Date: September 2020
Projected Completion Date: September 2021

Understand how we build parks.

Funding

Total Funding: $1,500,000
Funding Source: Borough President

Location

Glen Oaks Oval , Queens
260th Street and 74th Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/28/2020