Glen Oaks Oval Playground Reconstruction and Adult Fitness Equipment Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the playground and replace the basketball court with an adult fitness equipment area at Glen Oaks Oval.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: August 2019

Construction

Start Date: June 2020
Projected Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: $1,500,000
Funding Source: Borough President

Location

Glen Oaks Oval , Queens
260th Street and 74th Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 05/29/2020