Triborough Bridge Playground C Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct a dog run and reconstruct a basketball court at Triborough Bridge Playground C.
Project Timeline
Design
Start Date: January 2016
Projected Completion Date:
January 2017
Completion Date:
January 2017
Procurement
Start Date: January 2017
Projected Completion Date:
October 2017
Completion
Date:
November 2017
Construction
Start Date: April 2018
Projected Completion Date:
April 2019
Completion
Date:
March 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Triborough Bridge Playground C
, Queens
Hoyt Avenue North, Hoyt Avenue South, 23rd Street, 24th Street
Project Staff
Project Liaison: Joanne Amagrande
Contact NYC Parks
about this project
Last updated: 01/21/2021