Triborough Bridge Playground C Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a dog run and reconstruct a basketball court at Triborough Bridge Playground C.

Project Timeline

Design

Start Date: January 2016
Projected Completion Date: January 2017
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Completion Date: November 2017

Construction

Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $1,000,000
Funding Sources:
  • Borough President
  • City Council

Location

Triborough Bridge Playground C , Queens
Hoyt Avenue North, Hoyt Avenue South, 23rd Street, 24th Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/16/2019