Sunset Park Adult Fitness Area Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct a fitness area within Sunset Park.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: November 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $500,000
Funding Source: City Council

Location

Sunset Park, Brooklyn
Sunset Park, 41st Street opposite 6th Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 09/21/2017