McCarren Park Synthetic Turf Soccer Field Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct the existing multi-use synthetic turf field.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: May 2016
Projected Completion Date: December 2016
Completion Date: March 2017

Procurement

Start Date: March 2017
Projected Completion Date: December 2017

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $10 million
Funding Source: Mayoral

Location

McCarren Park, Brooklyn
McCarren Park, located along Lorimer Street, Between Driggs Avenue and Bayard Street, Borough of Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/20/2017