Ennis Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Ennis Playground.
Project Timeline
Design
Start Date: January 2016
Projected Completion Date:
January 2017
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
May 2018
Construction
Start Date: July 2018
Projected Completion Date:
July 2019
Completion
Date:
July 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Ennis Playground
, Brooklyn
11th Street, 12th Street, 2nd Avenue, 3rd Avenue
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 07/01/2022