Ennis Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    19% complete

This project will reconstruct Ennis Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: January 2016
Projected Completion Date: January 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: May 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $2,707,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Ennis Playground , Brooklyn
11th Street, 12th Street, 2nd Avenue, 3rd Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/15/2018