Scarangella Park Comfort Station Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct a new comfort station in Scarangella Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: August 2016
Projected Completion Date: November 2017
Completion Date: May 2018

Procurement

Start Date: May 2018
Projected Completion Date: February 2019
Adjusted Completion Date: September 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Scarangella Park , Brooklyn
Avenue V and West 13th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/01/2020