Friends Field Park Playground Expansion

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct portions of the existing playground, including the removal of the existing safety surface, and the expansion of the existing playground area.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: December 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: June 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Friends Field , Brooklyn
Friends Field Park Playground, Avenue L and East 4th Street, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/15/2018