Friends Field Playground Expansion

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct portions of the existing playground at Friends Field, including the removal of the existing safety surface, and the expansion of the existing playground area.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: December 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: June 2018

Construction

Start Date: September 2018
Projected Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $2,520,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Friends Field , Brooklyn
Avenue L and East 4th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/18/2018