Jacob Joffe Fields Adult Fitness Area Construction and Sport Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball and handball courts at Jacob Joffe Fields.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: September 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: February 2018

Construction

Start Date: April 2018
Projected Completion Date: April 2019
Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $886,000
Funding Source: City Council

Location

Jacob Joffe Fields , Brooklyn
Avenue K between 58th Street and 59th Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/20/2019