Asser Levy Park Playground & Path Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    99% complete

This project will reconstruct the playground and adjacent paths in Asser Levy Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: September 2016
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: October 2017
Completion Date: September 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018
Adjusted Completion Date: November 2018

Understand how we build parks.

Funding

Total Funding: $3,885,000
Funding Sources:
  • Mayoral
  • City Council

Location

Asser Levy Park , Brooklyn
West 5th Street between Surf Avenue and Sea Breeze Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 12/15/2018