Dyker Beach Park Synthetic Turf Soccer Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the existing synthetic turf soccer field, bleachers, and drinking fountain at Dyker Beach Park.

Project Timeline

Design

Start Date: February 2016
Projected Completion Date: August 2016
Completion Date: September 2016

Procurement

Start Date: September 2016
Projected Completion Date: June 2017
Completion Date: July 2017

Construction

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $1,555,000
Funding Source: City Council

Location

Dyker Beach Park , Brooklyn
14th Avenue between Benson Avenue and Bath Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 12/12/2018