Dyker Beach Park Synthetic Turf Soccer Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    15% complete

This project will remove the existing deteriorated synthetic turf and replace with new synthetic turf at soccer field. The existing aggregate base and sub-surface drainage system shall remain and be reconstructed if necessary. The existing bleachers and drinking fountain will be reconstructed or replaced.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2016
Projected Completion Date: August 2016
Completion Date: September 2016

Procurement

Start Date: September 2016
Projected Completion Date: June 2017
Completion Date: July 2017

Construction

Start Date: September 2017
Projected Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $1,695,000
Funding Source: City Council

Location

Dyker Beach Park, Brooklyn
North of Shore Parkway in Dyker Beach Park, West of 14th Avenue, between Benson and Bath Avenues

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/16/2017