Bronx and Queens Reforestation FY16 (CNYG-116 PLANYC)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    78% complete

This project will remove invasive species including trees over 1" up to and including 30" in diameter, shrubs, herbaceous plants and vines; excavate and clear sites (including removal of stumps and trees up to and including 6" in diameter); prepare tree pits; furnish, plant, maintain and replace various types of trees in prepared planting tree pits; and install of native seed mixes in and around areas with existing native species to be preserved; and install osprey nests.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: September 2015
Completion Date: November 2015

Procurement

Start Date: November 2015
Projected Completion Date: August 2016
Completion Date: July 2016

Construction

Start Date: July 2016
Projected Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $1,000,000
Funding Sources:
  • Mayoral
  • City Council

Location

Various locations in The Bronx and Queens

Project Staff

Contact NYC Parks about this project

Last updated: 11/02/2018