Bronx and Queens Reforestation FY16

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove invasive trees, shrubs, plants and vines; excavate and clear sites; remove tree stumps; prepare tree pits; furnish, plant, maintain and replace trees; install native seed mixes; and install osprey nests in the Bronx and Queens.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: September 2015
Completion Date: November 2015

Procurement

Start Date: November 2015
Projected Completion Date: August 2016
Completion Date: July 2016

Construction

Start Date: July 2016
Projected Completion Date: January 2019
Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $1,100,000
Funding Sources:
  • Mayoral
  • City Council

Location

Various locations in the Bronx and Queens

Project Staff

Contact NYC Parks about this project

Last updated: 07/19/2019