Sorrentino Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct portions of the Sorrentino Recreation Center.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: September 2015
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: January 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Sorrentino Recreation Center, Queens
18-48 Cornaga Avenue Queens, NY 11691

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 02/16/2018