Sorrentino Recreation Center Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    52% complete

This project will reconstruct portions of the Sorrentino Recreation Center.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: September 2015
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: January 2018

Construction

Start Date: March 2018
Projected Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $866,000
Funding Source: Mayoral

Location

Sorrentino Recreation Center , Queens
18-48 Cornaga Avenue Queens, NY 11691

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/15/2018