Sorrentino Recreation Center Boiler Reconstruction and HVAC Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    14% complete

This project will reconstruct boilers and provide a new heating, ventilation, and air conditioning system for the gymnasium at Sorrentino Recreation Center.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: April 2015
Projected Completion Date: June 2016
Completion Date: June 2016

Procurement

Start Date: June 2016
Projected Completion Date: March 2017
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: July 2018
Adjusted Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $1,369,000
Funding Source: Mayoral

Location

Sorrentino Recreation Center , Queens
18-48 Cornaga Avenue Between Beach 19th Street and Mott Avenue

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/15/2018