107th Street Pier Pavilion Demolition

  • Design
    30 % complete 
  • Procurement
     
  • Construction
     

This project will demolish the pier pavilion and install and reconstruct elements on the pier surface to provide for safe public access at 107th Street Pier.

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: February 2017
Adjusted Completion Date: May 2017

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $500,000 and $1 million
Funding Sources:
  • City Council
  • Borough President

Location

East River Esplanade , Manhattan
East River at East 107th Street, Borough of Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 04/27/2017