107th Street Pier Pavilion Demolition

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will demolish the pier pavilion and install and reconstruct elements on the pier surface to provide for safe public access at 107th Street Pier.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: February 2017
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: April 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

East River Esplanade, Manhattan
East River at East 107th Street, Borough of Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 02/22/2018

Was this information helpful?