St. Mary's Playground Multi-Purpose Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    4% complete

This project will reconstruct the existing multipurpose play area to include a skate park, basketball courts, multi-use synthetic turf field, adult fitness equipment and color seal coat walking track.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2015
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: July 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $914,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

St. Mary's Park, Brooklyn
Smith Street between Nelson and Luquer Streets, Borough of Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/22/2018