St. Mary's Playground Multi-Purpose Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    71% complete

This project will reconstruct the existing multipurpose play area at St. Mary's Playground to include a skate park, basketball courts, multi-use synthetic turf field, adult fitness equipment and color seal coat walking track.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: February 2015
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: July 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018
Adjusted Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $914,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

St. Mary's Park , Brooklyn
Smith Street between Nelson Street and Luquer Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 12/07/2018