NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Lt. Joseph Petrosino Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    2% complete

This project will reconstruct basketball courts, a playground, a spray shower, and adult fitness equipment, and construct new fencing, retaining walls, ramps, drainage, water supply, lighting, plantings, benches, synthetic turf, sidewalk and green infrastructure in Lt. Joseph Petrosino Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: January 2018
Completion Date: November 2017

Construction

Start Date: January 2018
Projected Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $3,945,000
Funding Source: Mayoral

Location

Lt. Joseph Petrosino Park, Brooklyn
Bounded by 70th Street, 16th Avenue, 71st Street, and New Utrecht Avenue, Borough of Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/22/2018

Was this information helpful?