Epiphany Playground Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the playground, spray shower, seating, handball and basketball courts, perimeter fence, and security lighting at Epiphany Playground.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: March 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: July 2018
Adjusted Completion Date: November 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Epiphany Playground , Brooklyn