Astoria Health Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    32% complete

This project will provide a complete and transformative reconstruction of Astoria Health Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: January 2018
Completion Date: March 2018

Construction

Start Date: March 2018
Projected Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $1,683,000
Funding Source: Mayoral

Location

Astoria Health Playground , Queens
14 Street between 31st Avenue and 31st Drive in the Borough of Queens

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/16/2018