Rev. Dr. Maggie Howard Playground Reconstruction
-
100% complete
-
100% complete
-
83% complete
This project will reconstruct the playground, multi-use fields, basketball and handball courts, and water features at Rev. Dr. Maggie Howard Playground.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: March 2016
Projected Completion Date:
August 2017
Completion Date:
December 2017
Procurement
Start Date: December 2017
Projected Completion Date:
September 2018
Completion
Date:
August 2018
Construction
Start Date: September 2018
Projected Completion Date:
March 2020
Adjusted Completion
Date:
April 2021
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Rev. Dr. Maggie Howard Playground
, Staten Island
Tompkins Avenue between Broad Street and Hill Street
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 02/26/2021