Rev. Dr. Maggie Howard Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    83% complete

This project will reconstruct the playground, multi-use fields, basketball and handball courts, and water features at Rev. Dr. Maggie Howard Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: August 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: August 2018

Construction

Start Date: September 2018
Projected Completion Date: March 2020
Adjusted Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $11,151,000
Funding Sources:
  • Mayoral
  • City Council

Location

Rev. Dr. Maggie Howard Playground , Staten Island
Tompkins Avenue between Broad Street and Hill Street

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 02/26/2021