Stapleton Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    44% complete

This project will reconstruct the playground, multi-use fields, basketball and handball courts, and water features at Stapleton Playground.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: August 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: August 2018

Construction

Start Date: September 2018
Projected Completion Date: March 2020
Adjusted Completion Date: June 2020

Understand how we build parks.

Funding

Total Funding: $11,151,000
Funding Sources:
  • Mayoral
  • City Council

Location

Stapleton Playground , Staten Island
Tompkins Avenue between Broad and Hill Streets

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 06/02/2020