Bloomingdale Park Synthetic Turf Field Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct a new synthetic turf multi-use field and reconstruct the existing synthetic turf soccer field at Bloomingdale Park.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: January 2016
Projected Completion Date: March 2017
Completion Date: September 2017

Procurement

Start Date: September 2017
Projected Completion Date: June 2018
Adjusted Completion Date: November 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Borough President
  • City Council

Location

Bloomingdale Park , Staten Island
Lenevar Avenue between Drumgoole Road West and Ramona Avenue

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 11/13/2018