Red Hook Recreation Area Ballfields 5-8 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    48% complete

This project will convert four ballfields from natural turf to synthetic turf and remediate contaminated soils at Red Hook Recreation Area.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: December 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: May 2018

Construction

Start Date: September 2018
Projected Completion Date: March 2020
Adjusted Completion Date: May 2020

Understand how we build parks.

Funding

Total Funding: $14,979,000
Funding Source: Mayoral

Location

Red Hook Recreation Area , Brooklyn
Lorraine Street, Bay Street, Hicks Street and Henry Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/05/2020