Sperandeo Playground Fence Height Extension

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    40% complete

This project will install fencing adjacent to the existing baseball backstop, with thirty foot (30’) tall steel posts, with twenty foot (20’) height chain link mesh affixed to the lower portion and ten foot (10’) height nylon netting affixed to the upper portion, in Sperandeo Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2014
Projected Completion Date: June 2015
Completion Date: June 2015

Procurement

Start Date: June 2015
Projected Completion Date: March 2016
Completion Date: June 2016

Construction

Start Date: November 2016
Projected Completion Date: November 2017

Understand how we build parks.

Funding

Total Funding: $240,000
Funding Source: Mayoral

Location

Sperandeo Brothers Playground, Brooklyn
Clevland Street between Atlantic and Liberty Avenues, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/20/2017