Queens Athletic Courts Reconstruction (QG-216M)

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct tennis, basketball and handball courts in Baisley Pond Park; basketball courts and an entry ramp at Police Officer Nicholas Demutiis Playground; and basketball and handball courts at Harvard Playground in Queens.

Project Update: This project was previously delayed and is now moving through the process.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: March 2017
Completion Date: April 2017

Procurement

Start Date: April 2017
Projected Completion Date: January 2018
Adjusted Completion Date: June 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 02/22/2018