Sperandeo Playground Sport Courts Reconstruction

  • Design
    100% complete 
  • Procurement
    100% complete 
  • Construction
    35% complete 

This project will reconstruct the basketball and handball courts.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2015
Projected Completion Date:June 2015
Completion Date: June 2015

Procurement

Start Date: June 2015
Projected Completion Date:March 2016
Completion Date: February 2016

Construction

Start Date: April 2016
Projected Completion Date:April 2017

Understand how we build parks.

Funding

Total Funding: $408,000
Funding Source:Mayor

Location

Sperandeo Brothers Playground, Brooklyn
Located at the corner of Liberty Avenue and Cleveland Street in the Borough of Brooklyn.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/13/2017