Pelham Bay Park Service Building Gas Line Construction and Heating System Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will install a new gas service line, remove oil tanks, and convert the building from oil to gas heat.
Project Timeline
Design
Start Date: November 2014
Projected Completion Date:
July 2015
Completion Date:
May 2016
Procurement
Start Date: May 2016
Projected Completion Date:
February 2017
Completion
Date:
July 2017
Construction
Start Date: March 2018
Projected Completion Date:
March 2019
Completion
Date:
March 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Pelham Bay Park
, Bronx
South side of City Island Road between Shore Road and Park Drive
Project Staff
Project Liaison: Michelle Martell
Contact NYC Parks
about this project
Last updated: 01/22/2021