Citywide Boiler and Heating Systems Reconstruction (CNYG-916MA)

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the boilers and heating systems at Prospect Park Paint Shop and Bensonhurst Senior Recreation Center in Brooklyn and at the comfort station in Mosholu Parkway in the Bronx.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: February 2013
Projected Completion Date: May 2016
Completion Date: September 2017

Procurement

Start Date: September 2017
Projected Completion Date: June 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $500,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 11/20/2017