Buono Beach Fountain Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the electrical and mechanical components of the fountain at Buono Beach in Alice Austen Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: March 2017
Completion Date: September 2017

Procurement

Start Date: September 2017
Projected Completion Date: June 2018
Adjusted Completion Date: February 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • Federal

Location

Alice Austen Park , Staten Island
Edgewater Street between Hylan Boulevard and Clifton Avenue

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 10/18/2018