Buono Beach Fountain Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the electrical and mechanical components of the fountain at Buono Beach in Alice Austen Park.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: July 2015
Projected Completion Date: March 2017
Completion Date: November 2019

Procurement

Start Date: November 2019
Projected Completion Date: August 2020
Adjusted Completion Date: February 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • Mayoral
  • Federal

Location

Alice Austen Park , Staten Island
Edgewater Street between Hylan Boulevard and Clifton Avenue

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 12/02/2020