Fort Greene Park Entrance Reconstruction and Drainage Improvements

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the park paths, staircases, entrances, drainage, and grading at Fort Greene Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: October 2015
Projected Completion Date: September 2016
Completion Date: May 2018

Procurement

Start Date: May 2018
Projected Completion Date: February 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Fort Greene Park , Brooklyn
South of Willoughby Avenue and north of the playground, and Myrtle Avenue Landscape north of Willoughby Avenue.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/18/2018