Idlewild Park Forest Restoration and Tree Planting

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    68% complete

This project will prepare planting sites for invasive species removals including the planting of new and replacement trees at Idlewild Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: February 2015
Completion Date: February 2015

Procurement

Start Date: February 2015
Projected Completion Date: November 2015
Completion Date: November 2015

Construction

Start Date: November 2015
Projected Completion Date: May 2018
Adjusted Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $1,700,000
Funding Source: Private

Location

Idlewild Park , Queens
Idlewild Park

 

Project Staff

Contact NYC Parks about this project

Last updated: 06/21/2018